richard grant and associates
Click here to return to the previous page These pictures were taken on 17 December 2003.The steel frame is now about 85% complete and brickies have commenced building the inner leaf of the outer wall. The remaining steel beams will be erected when the outer wall is complete as they span from the inner steel frame to the outer wall.Work closes down for the Christmas break in two days so there'll be nothing happening for two weeks.
|